Latest news: new picosecond accelerator operational - 23th of December 2009

Our new picosecond pulsed high-energy electron accelerator has delivered its first pulses today (23 December 2009). Pulses are being produced for pump and probe experiments with a world-wide unprecedented high repetition frequency of 100 Hz.

This terrific achievement is the outcome of intense collaboration and commitment of technicians and scientists at the Department of Chemical Engineering and the Reactor Institute Delft.

In particular Martien Vermeulen and Walter Knulst have shown enormous persistence since they started the design and construction of the accelerator about four years ago.

The electron pulses will be combined with optical and terahertz probe pulses for studies on new materials for application in opto-electronics (e.g. solar cells) and nanomedicine.


Movie of the electron beam - 23rd of December 2009



1 - The Sample Chamber has an extra port through which we can see the sample in the Sample Chamber from the front side. This makes is possible to place a CCD Camera behind this window and monitor the beam position and shape by using a phorphor screen at the sample position.


2 - The CCD image. In the center you can see the phosphor screen positioned in the center of the Sample Chamber.





Here you can see the movie with the electron beam visible on the phospor screen.

UV generated electron pulse - 23rd of December 2009

A view scope images. In purple the forward RF pulse, in green the reflected RF pulse, in light blue the beam dump signal measured over 50 Ohm.



1 - Clearly visible the large light blue spike which is the UV generated electron pulse measured in the beam dump.


2 - Same situation only now with the background of dark current visible. This can be achieved by changing the strength of the main magnet around the cavity.


3 - Now, we made the RF pulse shorter and changed the timing of the laser so that it arives at the end the RF pulse when the electric field in the cavity reaches it maximum.


4 - Zoom in at the end of RF pulse.

The Great Day - 23rd of December 2009

On the 23rd of December we prepared the UV laser beam and synchronization to excite the first electron pulses.


Walter Knulst and Martien Vermeulen who have contructed the picosecond-pulsed 4.5-MeV electron accelerator. This project could not have been successfull without the support and help of many people: John Suijkerbuijk, Paul Rijkers, Juleon Schins, Laurens Siebbeles, Rene den Oudsten, Raymon Bresser, Rene Gommers, Ruud van Tol, Eindhoven University of Technology, Pulsar Physics, and many others.



2 - On the scope screen in blue the UV excited electron pulse is visible. To celebrate this event a bottle of champagne is donated by Laurens Siebbeles, the initiator of the accelerator project.









3 - We invited a lot of contribitors to the construction of the electron accerlator to see the first electron pulses on screen and take part of the celibration.





4 - Taking a look at the setup.

5 - Taking a view at the setup.

Friday, November 2, 2007

Cavity Magnet installed and first test - 31th of October 2007

This week the Cavity Magnet is connected to its power supply and cooling water. Subsequently, the first field measurements are performed.



Xantrex XDC 30-400 HV Power Supply (12 kW)

The on-axis field maximum is reached at 0.481 T at a current of 400 A. The power consumption is about 10 kW.



More measurements are required to get the full magnetic field information. More important is the overlap of the magnetic axis with the geometrical axis of the accelerator cavity.

Tuesday, May 29, 2007

Highest RF peak power - 29th of May

Today we reached the highest peak power of RF. We measured 6.8 MW of RF. We hope to increase this soon to 10 MW by tuning all the parameters.

RF pulse from 2157A Klystron - 25th of May

In the figure you see the RF pulse (2998.5 MHz) produced by the 2157A Klystron. The modulator (ScandiNova AB) was operated at 165 kV, 4.9 us FWHM and 63 Hz. This is at full power level of 6.3 kW average power.

We have driven the input of the klystron at a low power (estimated at 2.5 W peak power, which is a tenth of the optimal power).

The output level measured by the RF diode detectors corresponds to 2.5 MW peak power. This corresponds to a small signal gain of +60 dB.

Friday, May 25, 2007

High Power RF Test - 23th of May

We have performed the first high power RF tests in May.

The RF setup is orginized in the following way:
- The output of the RF source, Phase-Locked Loop (PLL) Synchroniser, is fed to the 100-W continuous RF amplifier, MAL tld..
- Inside the PLL a RF switch is integrated at the output, so that we can produce a low power (13 dBm) RF pulse of tens of microsecond in duration.
- The MAL amplifier (type AM82-3S-45-50R) has a small signal gain of 41 dB and has a output maximum of 50.2 dBm.
- The output of the MAL amplifier is fed to the input of the Klystron Tube. The klystron tube has a small signal gain of 57 dB.
- At the output of the Klystron Tube the waveguide section (WR284) is mounted, which contains a circulator with load (Ferrite SC3-118), bi-directional coupler and RF pressure window (CPI VWX-1053) at the accelerator cavity.
- To the bi-directional coupler RF diode detectors (Agilent 423B) are connected to monitor the forward and reflected RF power.

In this test phase the RF pressure window is replaced by a reflection plate, so that all the RF power is dissipated in the RF load on the circulator.

In the control room we have placed all the measurement equipment: two puls generators to supply the trigger pulse for the modulator and RF switch inside the PLL Synchronizer. The signals are displayed on a oscilloscoop.

For the computer in the control room the modulator can be controlled and all the operating parameters can be monitored.

Upper: PLL Synchronizer, Lower: MAL RF Amplifier

N-type Coax cable connected to RF input of Klystron Tube.

Bi-directional coupler in waveguide section. RF diode detectors connected to forward and backward outputs.

Trigger signal generation and signal analyzing in control room.

Control computer in control room.

Red warning light indicates accelerator operation.

Wednesday, December 20, 2006

Modulator test 28th of November 2006

On this day we tested the modulator for the first time. The test was to check the pulses produced by the modulator without driving the klystron tube with RF power.

From the BNC output connectors the current and voltage pulses were obtained and recorded by an oscilloscope:



Note: The tension pulses are multiplied by a factor 2, because they were recorded using 50Ω termination, which causes the measured tension to be half of the proper value.